PROJECT AND PLANNING

  • The planning of the works is intended to reduce the nuisance to shopkeepers, residents, pedestrians and motorists, resulting from their implementation.

The works will start in May and will be carried out in a phased manner throughout the Central Axis and surrounding streets:

The phasing of the work will always ensure the existence of two-way circulation, per direction, throughout the entire axis, and of a road on each one of the side lanes of Avenida da República;

Parking is always guaranteed during the course of the works (in the intervention area and its surroundings);

The repaving of the pedestrian areas will ensure the existence of corridors of continuous circulation, access to commercial establishments and to the entrance to buildings;

The repaving of the lanes will be carried out during the night.